go to the Monitoring and controlled switching product page Amr Said asked on May 29th, 2015 in Monitoring and controlled switching

How to program the SwitchSync F236?

Tim Schulze-Koenig, Global Product Manager Monitoring

ABB's answer

Controlled switching is meant to minimize harmful transient effects and ultimately extend the life of electrical equipment. Each transient phenomena is unique, as it is related to the type of load, power system and substation characteristics. Because of this, there is no “standard” programming method of F236.

Certain minimum information is required, such as load type (is it a capacitor bank, filter bank, shunt reactor bank?) and circuit breaker type (is it an HPL420B2, or an HPL245B1?)

The best programming strategy is then decided based on said parameters.

Pls contact your local ABB to provide a technical training for those interested in further learning of controlled switching strategies and applications.

Like this answer 2 people liked it already!

0 Comments

or
Submit comment cancel

Area expert

  • Tim Schulze-Koenig

    Tim Schulze-Koenig

    Global Product Manager Monitoring

    High Voltage Products

Contact ABB

If you want to purchase a product, need any pricing information or need help or support from ABB, please contact your local partner.

Haven't found what you've been looking for?

or Ask a question or Contact ABB

ABB's website uses cookies. By staying here you are agreeing to our use of cookies. Learn more